MAJOR WATER SECTOR PROJECTS UNDER IMPLEMENTATION IN PAKISTAN | |||||
---|---|---|---|---|---|
Project | Location | App. Cost (Rs. in million) |
Live Storage | Irrigated Area (Acres) |
Status |
Basha Dam (Dam Part) | Khyber Pakhtunkhwa & Gilgit Baltistan | 510,000 | 6.40 | – | At initial stage |
Gomal Zam Dam | Khyber Pakhtunkhwa | 20,626 | 0.892 MAF | 191,139 (17.4 MW Power Gen.) | Completed & Operational |
Kachhi Canal (Phase-I) | Balochistan | 80,352 | – | 72,000 | Physically completed. (Phase-I) |
Darawat Dam | Sindh | 9,300 | 89,192 (Ac.Ft) | 25,000 (0.30 MW Power Gen.) | Physically completed |
NaiGaj Dam | Sindh | 26,236 | 160,000 (Ac.Ft) | 28,800 (4.2 MW Power Gen.) | 50 % Physical works completed |
KurramTangi Dam (Phase-I,Kaitu Weir) | Khyber Pakhtunkhwa | 21,059 | 0.90 MAF | 84,380 New 278,000 Existing (18.9 MW Power Gen.) |
17% works completed. Works at initial stage |
Naulong Dam | Balochistan | 18,027 | 0.20 MAF | 47,000 (4.4 MW Power Gen.) | Feasibility & Detailed Engn. Design completed Works on dam not yet started. |
Mohmand Dam | FATA Mohmand Agency | 114,285 | 0.676 MAF | 16,737 (800 MW Power Gen.) | Feasibility & Detailed Engn. Design completed Formulation of PC-I & Financial mechanism are in progress |
Right Bank Outfall Drain (RBOD) RBOD-I RBOD-II RBOD-III |
Sindh Sindh Balochistan |
17,505 61,985 10,804 |
– | ROBD-II will help to dispose 3,520 cusecs of drainage effluent into Sea received from RBOD-I & III |
82% completed 63% completed 74 % completed |